Project: Bevington School
The project required the construction of a new reception area and office accommodation with hi-spec fit-out together with the creation of a new external entrance area/play area; the contract was awarded on a two stage tender.
The school was fully occupied throughout the works.
Bevington School
- Value:
- £410K
- Programme:
- 20 weeks
- Client:
- Royal Borough of Kensington & Chelsea
- Consultant:
- Sproson Barrable
- Contract:
- JCT Minor Works Building Contract 2005 Edition
Construction Detail
-
Ceilings
-
Partitioning
-
Floor coverings
-
Sto render
-
External works
-
Electrical installation incl fire alarm
-
Fit-out
-
External & Internal redecorations
-
Piling & groundworks
-
Steelworks
-
Sundry repairs
-
Sarnafil roof covering